Power Automate Approval Workflows: Purchase Order, Leave, Expense and Invoice Examples
Four worked examples, from the trigger to where the decision is stored, then parallel approvals and timeout escalation step by step, plus the edge cases that break a simple flow: approvers on leave, edits after sign-off and the 30-day run limit.
SBy Shuvam, Founder of KodeBizUpdated
How a Power Automate approval workflow works
A Power Automate approval workflow is a cloud flow that starts when someone raises a request, such as a new item in a SharePoint list or a submitted Power Apps form, sends it to the right approver through the Approvals connector, waits for a decision, and writes that decision back to the request. Approvers respond from an actionable Outlook email, a Teams card, the Power Automate approvals center or the mobile app.
The usual building block is one action, Start and wait for an approval. Its approval type decides who must respond before the flow moves on:
- Approve/Reject - First to respond: any one assigned approver settles the request.
- Approve/Reject - Everyone must approve: every approver has to approve, and a single rejection ends it.
- Custom Responses: you define the options (say Approve, Reject, Send back) and wait for one response or all.
- Sequential approval: approvers respond one at a time in a fixed order; each must respond before the request moves on.
- Parallel approval is a pattern, not a type: separate approval actions in parallel branches, decided independently; later steps run once all branches finish. Example 5 below builds one step by step.
Example 1: purchase order and purchase requisition approval
For manufacturers and distributors, Power Automate purchase order approval is usually the first flow worth building. It starts as a purchase requisition approval workflow: a request for raw material, consumables or spares, raised from the store or shop floor and signed off by value.
- Trigger: When an item is created on a Purchase Requisitions SharePoint list, filled in directly or through a Power Apps form.
- Data captured: item, quantity, estimated value, vendor, cost centre, required-by date, quotation attached.
- Routing: the requester's manager, looked up in Microsoft Entra ID with Get manager (V2) from the Office 365 Users connector; the department head above a first threshold; a director above a second. Keep thresholds in a settings list so finance can change them without editing the flow.
- Approval type: Sequential approval when the levels are fixed. When the number of levels depends on the amount, branch on value with a Condition or Switch and chain one Start and wait for an approval per level.
- On approve: status Approved, PO number issued, buyer notified. On reject: status Rejected, comments sent to the requester.
- Record: decision columns on the requisition, plus a history list.
- What breaks, duplicate approvers: in a small company the manager is often also the department head, and Sequential approval does not allow the same approver at two steps, so remove duplicates first.
- What breaks, edits after sign-off: a flow that triggers only on creation never notices the quantity rising after approval. Store the approved value on the item, and run a second flow on When an item or a file is modified that uses Get changes for an item or a file (properties only) to send the request back when value, vendor or quantity changes. That action needs list versioning, and a trigger condition on the status column stops the flow's own updates from re-triggering it.
Example 3: Power Automate expense approval with receipts
Expense claims matter to manufacturers and distributors with field sales teams: fuel, tolls and customer visits, claimed from photos of paper bills.
- Trigger: a Power Apps form on the phone that saves the claim to a Claims list and calls the flow through the Power Apps trigger.
- Data captured: date, category, amount, customer or route, and a receipt photo.
- Routing: the manager for every claim; finance as a second step above a set amount or for travel.
- Approval type: Custom Responses - Wait for one response, with options such as Approve, Reject and Need a clearer receipt.
- On approve: marked for reimbursement, finance notified. On reject or send-back: returned to the requester with the comment.
- Record: decision, approver and comments on the claim, receipts attached.
- What breaks, trusted inputs: Microsoft advises validating values passed from Power Apps, so re-check amount and category in the flow.
- What breaks, receipt names: approvals cannot carry two attachments with the same name, and phone photos often share one, so rename each receipt first.
- What breaks, silence: a flow run lasts at most 30 days, pending approvals included, and Microsoft's known-issues page says an approval flow fails after waiting 28 days, leaving the request in the approvals center with nothing listening. Set an explicit timeout on the approval action (an ISO 8601 duration such as P3D) and configure the next step to run when it has timed out, so the claim escalates. Example 6 walks through that escalation step by step.
Example 4: a four-step invoice approval chain
This one is from a live system: the invoice approval in the ERP we built for King Stubb & Kasiva, a multi-office law firm. The requirement study found invoices took 12 days on average from draft to client send; one had been stuck for 41 days while the lead partner was in trial in another city.
Each step has its own SLA, and because the chain runs on Power Automate, a reminder fires every 24 hours while a step is stuck. Reminders, escalations and the audit trail are flows that change without redeploying the firm's React app, and the managing partner can change who escalates to whom herself. Invoices that took 12 days now go out in 2.
A send-back is where re-submission usually goes wrong. The returned request should reopen the same record and restart from the right step, with earlier comments kept and its history intact. The firm's four steps:
- Drafter: a junior associate pulls the matter's time entries, writes a one-line narrative for each and submits.
- Senior review: the lead lawyer adjusts entries and can send the draft back to the drafter with comments.
- Partner sign-off: the managing partner checks the total against the client's retainer or cap, then approves or rejects.
- Billing: a PDF with GST added and a locked sequential number, emailed from the matter record.
Example 5: parallel approval for a high-value purchase
Some requests need two departments to agree, and neither should wait for the other. A purchase above a set value, such as a new machine or a large raw material order, often needs Finance to confirm the budget and Operations to confirm the specification and vendor. Asking them one after the other doubles the wait. A parallel approval asks both at once.
There are two ways to build it in Power Automate, and they behave differently:
| One action, Everyone must approve | Parallel branches, one approval each | |
|---|---|---|
| What approvers see | The same title, details and attachments for everyone | Each department gets its own details, such as the budget line for Finance and the specification for Operations |
| On a rejection | One rejection ends the request for everyone | Each branch waits for its own answer, so a rejection in one does not stop the other |
| Timeouts and escalation | One timeout for the whole request | A separate timeout and escalation path per department |
| What you record | One outcome, with every approver's response in the action's outputs | One decision per department, written as separate history rows |
| Best for | A committee reviewing the same document | Departments that check different things |
Building the parallel approval, step by step
This version uses parallel branches, because Finance and Operations look at different things. It extends the requisition flow from Example 1.
- Step 1, the threshold: after the trigger, add a Condition that compares the estimated value with a parallel-approval threshold kept in the settings list, so finance can move it without editing the flow.
- Step 2, the Finance approval: in the Yes path, add Start and wait for an approval, type Approve/Reject - First to respond, assigned to the finance head, with the cost centre, budget line and value in Details.
- Step 3, the Operations approval: use Add a parallel branch beside the Finance approval and add a second Start and wait for an approval, assigned to the operations head, with the specification and vendor in Details and the quotation attached.
- Step 4, record each decision inside its own branch: after each approval, add a Create item on the history list with the outcome, the responder's name and email, the comments and the response date. Each department's decision is then on record even while the other branch is still waiting.
- Step 5, join the branches: add the next action below both branches, so it runs only when both have finished. A Condition there checks that the Finance outcome and the Operations outcome both equal Approve.
- Step 6, act on the result: if both approved, set the requisition to Approved and notify the buyer. Otherwise set it to Rejected and send the requester the comments from both departments.
- Variant, any one of a team: to let any of three finance managers sign, assign all three in the Finance approval with First to respond, separating their emails with semicolons.
- What breaks, the early rejection: when Finance rejects on the first day, the Operations request keeps waiting until it is answered or times out, and the flow cannot finish until then. If one rejection should close the whole request, use a single action with Everyone must approve, or give each branch a timeout as in Example 6.
Example 6: approval timeout, reminders and escalation
By default, Start and wait for an approval waits until someone answers or the run reaches its 30-day limit. That is how requests get stuck: the approver is travelling, the email is buried, and the requester has no way to move it. A timeout turns silence into a step the flow can act on.
Two details matter before you set one. The timeout goes in the action's Settings as an ISO 8601 duration: P3D is three days and PT12H is twelve hours. And it counts calendar time, not working days, so a request raised on Friday evening with P2D times out on Sunday evening. Choose the duration with weekends in mind, or keep working-day rules in a scheduled flow, described at the end of this example.
- Step 1, set the timeout: open the approval action's Settings and enter P2D in Timeout.
- Step 2, find the next approver: add Get manager (V2) from Office 365 Users with the original approver's email. In its Configure run after, clear is successful and tick has timed out, so it runs only when the approval went unanswered.
- Step 3, escalate: add a second Start and wait for an approval assigned to the manager's email, with the original details and a first line that says why it reached them, such as Escalated after two days without a response.
- Step 4, cover a missing manager: Get manager (V2) fails when no manager is set in Microsoft Entra ID. Add a step that runs after Get manager has failed and assigns the escalation to a fallback approver from the settings list.
- Step 5, record the escalation: write an Escalated row to the history list with the original approver, the new approver and the time, so the audit trail shows why someone else decided.
- Step 6, carry on from either path: store the outcome in a variable after the first approval and again after the escalation. On the normal path the escalation steps never run, so configure the step that follows them to run when they are successful or skipped.
- Variant, reminders before escalating: split the request into Create an approval and Wait for an approval. In a parallel branch, a Do until loop waits one day with a Delay and sends a reminder while a Responded variable is still false; the branch with Wait for an approval sets it to true. Raise the loop's Count and Timeout limits, because by default a Do until loop stops after 60 iterations or one hour.
- What breaks, the 30-day ceiling: a timeout cannot stretch a run past 30 days, and an approval flow fails after 28 days of waiting. For approvals that can sit for weeks, such as capital spend waiting for a board meeting, keep the status on the SharePoint item or Dataverse row instead. One flow creates the approval with Create an approval, another acts on the response, and a scheduled flow runs each morning to find requests still pending past their due date and send reminders or escalate. Because that scheduled flow decides what counts as overdue, it can skip weekends and holidays kept in a list.
The audit trail: store the decision with the record
An approval given in email is hard to prove later. The thread gets forwarded, a reply says "ok, go ahead" without naming a version, and the person who knew the context leaves. When an auditor asks who approved a purchase order, and at what value, nobody should be searching an old mailbox.
The flow's run history is not an audit trail either, because Power Automate keeps run history for only about a month. The approval's outputs already carry what you need: the outcome and, for each response, the approver's name and email, the comments and the response date.
Write them to the record or a linked history list, append-only: a new row for every event, never an overwrite. A SharePoint list keeps the flow on standard connectors; Dataverse tables suit approvals inside a larger Power Apps system, but the Dataverse connector is premium. At every step, record:
- The decision and the step it belongs to
- The approver's name and email as they were at the time
- Request and response timestamps in UTC (as the Approvals connector reports them), converted only for display
- Comments, and the exact value or version that was approved
- Reassignments, escalations and send-backs as separate entries
How we approach approval workflows at KodeBiz
We start with a requirement study, tracing real requests with the people who raise, approve and audit them. That is where exceptions surface: the urgent PO that skipped a level, the claim approved on WhatsApp, the director with no manager in the directory. Thresholds, stand-ins, SLA windows and send-back rules go into a written scope the client agrees before any flow is built, and the timeline is agreed then too.
Design and build follow that scope: Power Automate when approvers live in Outlook and Teams, custom Node services when routing is too branchy for a flow. Our article on Power Automate vs custom code (Node.js) sets out where we draw that line. Testing runs sample requests through every route, including parallel branches, timeouts, delegation and edits after approval. Then we train requesters and approvers, go live, and stay on for support, adjusting thresholds and routes as policy changes.
Frequently asked
How do I build a multi level approval workflow in Power Automate?
Use the Sequential approval type in Start and wait for an approval, with one Assigned To entry per level, or chain several Start and wait actions, each followed by a condition on the response. Get manager (V2) finds each level in Microsoft Entra ID. When levels depend on value, branch on the amount first, and record the decision after every level.
How do I set up a parallel approval in Power Automate?
Add a Start and wait for an approval for the first approver, then use Add a parallel branch to put a second approval beside it, each with its own details. Place the next step below both branches so it runs once both have answered, and check that both outcomes equal Approve. If one rejection should close the request for everyone, assign both approvers in a single action with Approve/Reject - Everyone must approve instead.
How do I escalate a Power Automate approval if nobody responds?
Set a Timeout on the approval action in its Settings, as an ISO 8601 duration such as P2D. Then add Get manager (V2) and a second approval, configured to run after the first has timed out, and record the escalation on the request. The timeout counts calendar time and no run lasts beyond 30 days, so working-day rules and long waits belong in a scheduled flow that reads a status column.
Can a Power Automate approval wait longer than 30 days?
Not inside one flow run. A run is limited to 30 days, pending approvals included, and Microsoft notes an approval flow fails after 28 days of waiting. For longer approvals, use two flows: one creates the request with Create an approval, the other acts on the response, with approvals stored in Dataverse.
What happens to a Power Automate approval when the approver is on leave?
By default it waits. The approver can reassign it from the approvals center, but the requester cannot. Build delegation into the flow instead: check a delegation list or the approver's out-of-office status before assigning, and set a timeout on the approval action so an unanswered request escalates.
Do Power Automate approvals need a premium licence?
Not for the approval itself. The Approvals connector is standard, and so are SharePoint and Office 365 Users, so a flow built from those runs on an Office 365 licence that includes Power Automate. Premium connectors such as Dataverse and HTTP change that.
Sources
- Get started with Power Automate approvals, Microsoft Learn
- Manage parallel approvals, Microsoft Learn
- Manage sequential approvals, Microsoft Learn
- Known issues with approvals, Microsoft Learn
- Limits of automated, scheduled and instant flows, Microsoft Learn
- Office 365 Users connector reference, Microsoft Learn
Power Automate vs custom code (Node.js)
Where a flow stops being the right tool and routing or rules belong in a tested service.
ServiceApproval workflows
Multi-stage approvals with routing, escalation, and a full audit trail.
ServicePower Automate
Automate approvals and SLA timers across the Microsoft 365 tools you already use.
ServicePower Apps
Low-code apps on Dataverse when your team already lives in Microsoft 365.